Cambridge Elementary

Updated October 31, 2018
Cambridge teachers, parents, and staff have been heavily involved in the design of the new playground.  A community meeting was held the evening of Monday, October 23, to share information and gather input from the Cambridge community.  The Cambridge playground and other campus upgrades have come before the AHISD Board of Trustees during several board meetings.

New Fine Arts
Program/Design  August 2017 - October 2017
Construction Doc  November 2017 - March 2018
Bidding  April 2018 - May 2018
Construction  June 2018 - July 2019


 Install 4 Portables  June 2018
 New Playground  May 2019 - July 2019
 New Parking  June 2019 - August 2019



Progress
October 29, 2018 - Steel framing and interior CMU wall construction have commenced.
Image of Cambridge Elementary construction Image of Cambridge Elementary construction Image of Cambridge Elementary construction

October 29, 2018 - Landscaping along Townsend and Cambridge Oval is complete. 
Image of Cambridge Elementary  Image of Cambridge Elementary

September 29, 2018 - The concrete slab has been poured for the Fine Arts Building and steel will be erected in October 2018.
Image of Cambridge Elementary concrete slabImage of Cambridge Elementary concrete slab

Click pictures to expand



Image of Cambridge bond update
Image of Cambridge Elementary

Image of Cambridge Elementary plantings

Image of Cambridge Elementary
Image of Cambridge Elementary

Image of Cambridge Elementary

 

AHISD welcomes patrons comments on any of the facility drawings.
Please email Mike Hagar at mikeh@ahisd.net

Website by SchoolMessenger Presence. © 2018 West Corporation. All rights reserved.