Bond 2023 Updates

Bond 2023 Logo with Blueprint Icon

Alamo Heights ISD voters overwhelmingly approved three bond propositions in May 2023. Bond 2023 will provide updated learning spaces at all campuses, continue to address safety and security, and allow the district to be better community partners with additional parking, improved traffic flow, and outdoor and meeting spaces for community use.

The work will be divided into three project packages. Planning for Package One began in summer/fall 2023. AHISD is committed to sharing regular updates about the design, planning, and construction phases during this exciting time for the district.

The new high school schematic design was shared at the January 2024 Board Meeting. Construction at AHHS is expected to last from May 2024 until August 2026.

Rendering of front of proposed AHHS building

Package One also includes the relocation of the Excel Academy and Connects program to the current AHISD Central Office and the construction of a new Central Office/Learning Center for our school community.


October 2024 


The official start of fall brought a new phase in construction at Alamo Heights High School. After months of demolition work and the haul off of debris, the new building is now under construction.

In mid October, crews began site grading, earthwork, and utility work which included drilling piers and prepping to pour foundation. A tower crane was also erected at the site. This type of crane will keep the existing trees safer as the new building is constructed.




September 2024 


During the month of September, demolition and debris haul-off continued at Alamo Heights HS. A little less than 600 truckloads of materials were hauled away during this process. In October, crews will break ground on the new building and enter a new phase of the construction process. The project remains on time and on budget.

Also in September, the beloved Mule statue was reinstalled by the north entrance to Orem Stadium. 



August 2024 


August brought the start of the school year and students and staff are back on the Alamo Heights HS campus adjusting to the new set up during construction. Teachers did a wonderful job setting up classrooms and making ‘the Mods’ feel like home. Many classrooms are larger than what they had in the previous building.

Demolition work continued in a major way with most of the main building demolished in August. The haul off of debris is underway.

The Broadway North parking lot (formerly the Colony House apartments) was completed this month and will be ready for student permit parking in addition to the Broadway South parking lot. With these two lots, there are actually more parking spots available on campus than last year.

The Bond Community Council met in mid August and after receiving updates from LPA Architects and the District’s Bond Manager, the group toured the modular classrooms and the new temporary library space. Trustees also toured the spaces this month.



Construction Schedules/Timeline


Bond construction will be divided into three project packages.

Package One
Alamo Heights High School - construction May 2024 to August 2026
Central Office/Learning Center - construction June 2026 to August 2027
Excel Academy/Connects - construction May 2027 to December 2027

Package Two
Robbins Campus (located next to Tennis Center/Natatorium and current home of Excel and 09 Academies)
Softball Field and Accessory Buildings - construction January 2025 to December 2026
Tennis Improvements - construction January 2025 to December 2025
Baseball Improvements - construction January 2025 to December 2025
Robbins Building Removal and New Parking lot - construction January 2028 to June 2028
Cambridge Elementary School - construction March 2025 to August 2026
Woodridge Elementary School - construction June 2025 to August 2026
Plant Services - construction September 2025 to May 2026

Package Three
Howard Early Childhood Center - construction May 2026 to July 2027
Alamo Heights Junior School - construction April 2027 to June 2028

Visit the Construction Timeline page to see how construction will impact AHISD learners.

All dates slated for campus construction projects are subject to change due to factors like weather.


Keeping the Community Informed

Regular bond construction updates will be provided at Board Meetings, in the School Views publication mailed to AHISD residents three times a year, on this website, and on district social media platforms.

Who’s involved
Committees - AHISD Board of Trustees and Building Committee; Campus committees; and Bond Community Council

Architect - LPA Design Studios
General Contractor - Bartlett Cocke General Contractors
AHISD Construction Manager- Mike Hager

Contact Us
Direct any questions about AHISD Bond 2023 to Construction Manager Mike Hagar.