Cambridge Elementary

Updated August 29, 2019
Cambridge teachers, parents, and staff have been heavily involved in the design of the new playground.  A community meeting was held the evening of Monday, October 23, 2018, to share information and gather input from the Cambridge community.  The Cambridge playground and other campus upgrades have come before the AHISD Board of Trustees during several board meetings.

New Fine Arts
Program/Design  August 2017 - October 2017
Construction Doc  November 2017 - March 2018
Bidding  April 2018 - May 2018
Construction  June 2018 - April 2019


 Install 4 Portables  June 2018
 New Playground  May 2019 - August 2019
 New Parking  June 2019 - August 2019



Progress
September 30, 2019 - Community play area is complete.
 Cambridge community play area  Cambridge community play area is complete
August 29, 2019 - New play area and track are complete.  New staff parking is open across Ogden. Community play area is slated to be complete in September.
 Aerial of Cambridge Elementary Track  Cambridge Elementary playground  
June 18, 2019 - Portables are gone and work has commenced for the new play area and playing field/track. 
 Cambridge Elementary has commenced on new play area
April 30, 2019 - The first grade class made the construction team a banner, gift bags, and cheered them on to the finish!  The building is complete and teachers are moving in.  Work continues on the landscaping in front of the new Fine Arts Building.  Portable have been removed so work can commence on the new play area and playing field/track.
Thank You banner for construction workers Orchestra Room at Cambridge
Entry Hall of Fine Arts Building Instrument Storage in classroom Planting beds
Art Classroom
March 22, 2019 - All exterior doors and windows have been installed.  Concrete floors have been polished in Art Classrooms and corridors.  Vinyl flooring and mirrors have been installed in Orchestra and Music Classrooms.  Acoustical panels have been installed in all classrooms.  Millwork has started to be installed in all spaces.  Tile backsplashes and feature walls are in place.  Ceiling-mounted power reels are installed in Art Classrooms.
Image of Cambridge Construction  Image of Cambridge Construction  Image of Cambridge Construction
Image of Cambridge Construction  Image of Cambridge Construction  Image of Cambridge Construction
Image of Cambridge Construction  Image of Cambridge Construction
February 8, 2019 - ID'Hanis block feature wall has been installed.  Dry wall and roof work continues. Roof top mechanical equipment has been set.

Image of Fine Arts Porch    Image of Roof Top Equipment

 Image of Corridor leading to gym     Image of D'Hanis feature wall
January 9, 2019 -Installation of masonry and a new fire line is underway.  Windows have been installed.  Insulation and gypsum board are being installed in classroom spaces.
 Image of Cambridge Art Classroom  Image of Cambridge Fine Arts Entry
Image of Cambridge Fire Line Install  Image of Cambridge Masonry  Image of Cambridge Orchestra Classroom
December 2, 2018 - Roof work has commenced on the Fine Arts Building.  Exterior waterproofing and insulation are being installed.  Interior metal stud framing is underway.  Scaffolding is erected and brickwork is scheduled to start soon.
 Image of Cambridge Elementary construction  Image of Cambridge Elementary construction

Image of AHHS Commons Construction  Image of Cambridge Elementary construction  Image of AHHS Commons Construction
December 2, 2018 - Canopy framing is underway. 
 Image of Cambridge Elementary Fine Arts       Image of Cambridge Elementary Fine Arts
October 29, 2018 - Steel framing and interior CMU wall construction have commenced.
Image of Cambridge Elementary construction Image of Cambridge Elementary construction Image of Cambridge Elementary construction

October 29, 2018 - Landscaping along Townsend and Cambridge Oval is complete. 
Image of Cambridge Elementary  Image of Cambridge Elementary

September 29, 2018 - The concrete slab has been poured for the Fine Arts Building and steel will be erected in October 2018.
Image of Cambridge Elementary concrete slabImage of Cambridge Elementary concrete slab

Click pictures to expand

 
 
 
 
 
 


Image of Cambridge bond update
Image of Cambridge Elementary

Image of Cambridge Elementary plantings

Image of Cambridge Elementary
Image of Cambridge Elementary

Image of Cambridge Elementary

Cambridge teachers, parents, and staff have been heavily involved in the design of the new playground.  A community meeting was held the evening of Monday, October 23, 2018, to share information and gather input from the Cambridge community.  The Cambridge playground and other campus upgrades have come before the AHISD Board of Trustees during several board meetings.

AHISD welcomes patrons comments on any of the facility drawings.
Please email Mike Hagar at [email protected]