Gyms/Athletic Complex

Updated June 11, 2020

Gyms
Program/Design  November 2017 - April 2018
Construction Doc  May 2018 - February 2019
Bidding  March 2019 - April 2019
Construction  June 2019 - September 2020

 

Progress
June 11, 2020 - Concrete block installation is ongoing.  Plumbing and electrical rough in work is ongoing.  Mechanical ductwork is being installed. Steel for Gymnasium roof is in place.  Other steel beams and joists continue to be installed.
 Construction of Athletic Building  Construction of Athletic Building
Construction of Athletic Building  Construction of Athletic Building
Construction of Athletic Department  Construction of Athletic Building
May 21, 2020 - Concrete slabs continued to be poured.  Concrete block installation is ongoing.  Plumbing and electrical rough in work is ongoing.  Mechanical ductwork is being installed. Steel for Gymnasium roof is in place.  Other steel beams and joists continue to be installed.
 AHHS Athletics Concrete Clock  AHHS Athletics First Girder
AHHS Athletics Plumbing and Mechanical work  AHHS Athletic Plumbing  AHHS Sky Gym with new locker rooms
Athletics Slot Drain for Showers  Athletics Steel Erection at Dance Gym  Athletics Steel Girders
February 18, 2020 - First and second floor concrete slabs are being placed.  Concrete columns are being poured.
 AHHS Athletics Second Floor Formwork  AHHS Athletics Second Floor Pan Forms
AHHS Athletics Utility Trenches AHHS Athletics
January 7, 2020 - Foundation prep continues.  Concrete slabs are being placed in sections.
 AHHS Athletics concrete pour  AHHS Athletics Foundation prep
AHHS Athletics Foundation prep  AHHS Athletics Beam trenches
AHHS Athletics Existing weight room
August 29, 2019 - The courtyard, Annex, and Muledome are demolished.  The skin of the Sky Gym has been removed.
 Sky Gym demolition    Sky Gym demolition
 
 
 
 