Construction Schedules/Timeline
Bond construction will be divided into three project packages.
Package One
Alamo Heights High School - construction May 2024 to August 2026
Central Office/Learning Center - construction June 2026 to August 2027
Excel Academy/Connects - construction May 2027 to December 2027
Package Two
Robbins Campus (located next to Tennis Center/Natatorium and current home of Excel and 09 Academies)
Softball Field and Accessory Buildings - construction January 2025 to December 2026
Tennis Improvements - construction January 2025 to December 2025
Baseball Improvements - construction January 2025 to December 2025
Robbins Building Removal and New Parking lot - construction January 2028 to June 2028
Cambridge Elementary School - construction March 2025 to August 2026
Woodridge Elementary School - construction June 2025 to August 2026
Plant Services - construction September 2025 to May 2026
Package Three
Howard Early Childhood Center - construction May 2026 to July 2027
Alamo Heights Junior School - construction April 2027 to June 2028
Visit the Construction Timeline page to see how construction will impact AHISD learners.
All dates slated for campus construction projects are subject to change due to factors like weather.